Red Oak levee review heads to next phase

The Red Oak City Council heard some positive news regarding the community’s levee recertification project.
Dan Fricke with JEO Consulting attended last week’s council meeting to give an update on the start of the second phase of the project. Fricke said based on preliminary results, the bulk of the levee elevation is just right.
‘The height of the levee drives a lot of the cost of improvements, if necessary. For most of the levee, there are no height improvements required, which is good news,” Fricke said.
Fricke added that recent data from the Iowa Flood Center would likely contribute to removing the leftover areas of concern that don’t meet the height requirements.
“With some of the information from the Iowa Flood Center, in general, we believe all the areas of concern will go away, and there will be no height issues. Some of the phase two work will be coordinating with FEMA the results of the Iowa Flood Center data,” Fricke advised.
One of the areas of concern was a levee tie-in with the Burlington Northern Railroad grade. At the time, the practice was acceptable, and now it is not. With the Iowa Flood Center data contributed in, Fricke said, on paper, the results may lead to remapping.
“Essentially what would happen is, based on the data, the water surface elevation may be re-mapped. If they accept the data, there would be no flood hazards against the town from Red Oak Creek,” Fricke said.
Geotechnical analysis is one of the more costly parts of the projects, and Fricke said that cost will be figured into the phase two cost of the project. Fricke had high hopes for the results of the Iowa Flood Center data being good news for the city.
“Your levee is built so high relative to the base flood elevation, that I speculate and am fairly confident that the geotechnical analysis will pass,” advised Fricke.
City Administrator Brad Wright said the key element of phase two will be getting FEMA to accept the data from the Iowa Flood Center.
“If we fail on that, this becomes much more complicated. We then come to having a major issue in town from the water coming back from the south, or having to extend the levee south of the Burlington Northern Rail Line and tying into high ground. We’ll be approaching a million dollar project in a hurry if we’re forced to extend the levee,” Wright said.
Wright believed the data would be acceptable to FEMA, as an unbiased agency submitted the data, rather than a biased agency the city was paying for.
Fricke has outlined the proposal for phase two, and the council will vote on the go-ahead to JEO engineering at their next council meeting.
In other business, the council:
Renewed a Class C liquor license for Johnny’s Stakhouse.
Approved a resolution setting deficiency assessments and schedules of payments with certification.
Approved a change order to Henningsen Construction on the street project, adding additional days to the project for intake adjustment and replacing non-servicable manhole castings.
Heard an update from City Engineer Pete Crawford. Crawford advised work on the fire station roof will soon be underway, with the contractor working through the winter months. The fire station will remain open 24/7 for business as usual.