Bike trail construction finally completed

 While the work is nearly done on the next section of the Red Oak trails, the contractor that did the work may have a tough time collecting the entire payment after finishing the job a month late. 

Red Oak City Administrator Brad Wright said Carley Construction, was scheduled to have completed the 1,200-foot concrete trail running parallel to the high school parking before classes resumed Aug. 12. 

Instead, the Treynor-based company began work Aug. 13, finally pouring the concrete last week. Work is expected to be finished by Monday of this week, including planting grass seed on both sides of the trail. 

However, according to the contract agreed upon by the city, Carley Construction and the Department of Transportation, which provided most of the project’s funding, the contractor’s payment can be reduced by as much as $800 per day after 20 working days passed.

The contract specified a start date of July 21, but Carley Construction has sent a letter to Crawford and the DOT objecting to the working days schedule, which determines the final payment. 

“When it costs him $800 a day until the job is done, he’s going to fight it with all his means,” Crawford said. 

However, after an incident in the school parking lot in which a student rear-ended a piece of heavy equipment, Wright said he’s far less inclined to negotiate with the contractor. 

“To have a piece of equipment driving down a school lane is pretty poor judgment,” Wright said. “In the past, we have been pretty flexible with the working days, but we are pretty frustrated and will be charging the full $800 a day.”

Carley Construction was also the contractor for the downtown street/sidewalk project that was also riddled with delays. 

Crawford said this is the third of four sections of the first phase of the trail that once completed, will encompass all of Red Oak. 

Funding has been secured for the fourth section, which includes improving the cemetery road and its broken asphalt, where it connects with the end of section three on 8th street. 

A portion of the trail, which is currently gravel and located on the fairgrounds, could be asphalted as part of the fourth section, should a funding agreement be reached between Red Oak and Montgomery County officials. 

Research has begun on Phase 2 of the trail, which will include taking the trail across Highway 48 towards the levy. 